Editorial section

Social

Resettlement, community consultation, working conditions, grievance mechanisms and GBV prevention: the social requirements of DFI-funded projects.

Articles

Long reads

15 / 8 published

Labour influx: anticipating impacts on host communities

A large construction site attracts workers, but also vendors, transporters and families. Within a few months, a rural locality sees its population swell, its rents rise and its health centre become saturated. These effects are not random. They can be anticipated, assessed and managed.

16 July 202610 min

Consultation and participation: conducting successful focus groups in rural areas

A failed consultation is not visible on the day itself. Everyone has spoken, the photos are taken, the minutes are signed. The defect appears during due diligence, when the lender asks who was in the room, who was not, and what the absent would have said. The focus group is the tool that determines this answer.

30 June 202610 min

Contractors' workers: how far does the developer's responsibility extend

On a large construction site, the developer rarely employs the majority of the people working there. Earthworks, formwork, security, catering, transport: everything goes through contractors. Yet IFC PS2 refuses to allow this delegation to dilute responsibility. It draws a precise line between what the client must guarantee and what remains outside its control.

11 June 202610 min

SEA/SH on construction sites: from code of conduct to effective sanctions

A code of conduct signed by all workers protects no one if no sanction is ever imposed. On a construction site, sexual exploitation, abuse and harassment are prevented by written rules, but only recede if those rules have consequences. This article follows the chain, from the displayed code of conduct to the sanctions that lenders actually verify.

4 June 202611 min

Grievance mechanism: sizing a credible GM for a rural project

The principles of a good grievance mechanism are well known. Their translation into a rural setting is less so. A locked complaints box in a hamlet three hours from the nearest track, a written procedure in a language few people read, a deadline based on working days: all mechanisms compliant on paper and dead on the ground. Sizing means adapting each parameter to the actual context.

26 May 202610 min

Cut-off date: setting it, communicating it, defending it

A date stops the count. Before it, one is surveyed and eligible for compensation. After it, one becomes an opportunistic occupant. The cut-off date determines this shift, and its robustness is decided well before the first challenge.

7 May 202610 min

Resettlement: distinguishing physical displacement from economic displacement

Anyone who loses their home is displaced. Anyone who loses their field is also displaced, even if they sleep in the same bed at night. Project teams see the first case and forget the second. The lender counts both.

21 April 202611 min

DFI social reporting: key indicators, frequency and format

Social reporting for a project under DFI financing is one of the deliverables that most proves, or defeats, an E&S arrangement over time. A report that conceals difficulties breeds mistrust; a report that presents them with lucidity builds trust. Indicators matter, but prose matters just as much.

25 February 20268 min

E&S Consultant or Internal E&S Directorate: Which Organisation for Your Project

The choice between an internal E&S directorate and the use of external consultants is not binary. It is a question of organisational architecture that conditions the maturity of the system over five to ten years. Properly framed from the outset, it structures the project's credibility vis-à-vis lenders and stakeholders.

23 February 20268 min

Social due diligence: what lenders examine before approving financing

Social due diligence is the stage at which a lender decides whether or not to trust a borrower. The documents produced are important, but what is at stake is more subtle: the coherence of the whole, the institutional maturity, the weak signals that the file allows to filter through. No presentation rule can substitute for this reading.

13 February 20269 min

Working Conditions on DFI-Financed Projects: Requirements and Key Points

On a construction site under international financing, national labour law is merely a floor. DFIs superimpose a contractual standard that extends to contract workers, subcontractors and, partially, to the primary supply chain. The gap with local practice is sometimes considerable.

10 February 20269 min

FPIC: how to obtain genuine and documented community consent

Consulting is not consenting, informing is not enlightening, and a decision taken under schedule pressure is never free. FPIC (Free, Prior and Informed Consent) is the highest requirement on the community engagement ladder. Obtaining it genuinely requires a methodology for which few projects are prepared.

7 February 20269 min

GBV in infrastructure projects: from policy to operational action plan

An infrastructure construction site concentrates known risk factors for gender-based violence: influx of labour, economic asymmetry with communities, temporary facilities, strong site hierarchies. A serious GBV action plan does not stop at awareness training; it structures five operational components and lasts the full duration.

5 February 20269 min

Grievance Mechanism: Designing an Accessible and Credible System

The grievance mechanism is the social health indicator of a project. A mechanism that receives nothing is rarely a perfect project; it is almost always an inaccessible or delegitimised system. What lenders examine can be read in a few simple indicators.

26 January 20268 min

RAP (Resettlement Action Plan): step-by-step guide for any project displacing populations

On an infrastructure project, nothing is harder to remedy than a poorly conducted RAP. It is the deliverable that engages the project owner's reputation for ten years. Its quality hinges on six stages, all visible from the lender's due diligence.

8 January 20269 min
Practical sheets

Short references, ready to use

Checklist
4 min

Stakeholder mapping template

3 axes of analysis, power/interest scale, quarterly update — the format I maintain across all my projects.

Coming soon →
Checklist
5 min

Operational grievance mechanism: 12 criteria

The points that E&S teams of lenders (AfDB, IFC, BII) actually verify in review.

Coming soon →
Standard procedure
6 min

Preparing a community meeting in a rural area

Logistics, translation, timing, gender, closing protocol — the preparation that makes the difference.

Coming soon →
Practical memo
5 min

PS5 — the census of PAPs without missing anything

Minimum variables, collection tools, quality controls. What a robust RAP requires from day 1.

Coming soon →
Monitoring tools

Templates and trackers for project oversight

Stakeholder Consultation Register

Excel

Log of meetings, participants, languages, issues raised, commitments made, action tracking. Time-stamped, signed, exportable.

Grievance tracking register

Excel

Recording, categorisation, processing SLA, resolution status, complainant satisfaction. Compliant with IFC PS1 / AfDB OS1.

Post-resettlement RAP monitoring

Excel + Word

Livelihood restoration indicators, payment tracking, PAP satisfaction, complaints evolution.

Construction Site Social Indicators

Excel

Local employment, gender balance, training, health and safety, community incidents — monthly dashboard ready to share with the lender.